Access to EMTP user presentations, webinars, and slide deck presentations.
31 presentations for Overvoltage:
Author(s): Andreia Leiria
Type:Technical Presentation
Date: 2021-09-02
Abstract
Overvoltages were identified on the MV and LV networks of a Hydro Power Plant as the cause of the trip of the LV maximum voltage protection, compromising the normal operation of the system. Following ... see morethis event, measurements were conducted and the presence of a very high 23rd harmonic, potentially responsible for the various overvoltages, was identified associated to the operation of the Plant’s Synchronous Machine Frequency Control System (FCS). It was concluded then that this harmonic would have its origin in the FCS and would be amplified due to a possible resonance in the Power Plant internal network. A digital simulation study, using EMTP, was conducted to identify and characterize the resonance in the system and to propose mitigation solutions. The simulation models were developed using the equipment data and the system characteristics. The models were duly validated with measurements made both in time and frequency domains and it was possible to identify the origin of the overvoltages and their propagation in the system. It was concluded that the resonance occurred between a 30/11 kV Power Transformer and a 30 kV cable with 850 m.
This conclusion was supported by the results obtained in the measurements. Several alternatives were analyzed as mitigation solutions: - Installation of capacitors; - Different bonding techniques of the 30 kV cable sheaths; - Changing the 30 kV cable length; - Installation of a harmonic filter; The advantages and disadvantages of each solution were weighed also considering the ease of implementation, namely the available room. It was concluded that the installation of capacitors would be the best option. Measurements were conducted after the capacitor’s installation confirming the success of this solution.
Tag(s): harmonics, power uality, resonance
Author(s): Jin Yang - Ener-Phase Solutions
Type:Technical Presentation
Date: 2021-06-21
Abstract
A case study will be presented demonstrating modeling of overvoltage in a moderately sized system involving medium voltage vacuum breakers, cables and transformers. The focus is on simulating high fre... see morequency overvoltage generated by circuit breaker prestrikes and re-ignitions and evaluating the impacts on transformer insulation.
-Results obtained from a customized breaker TRV model which is capable of controlling the capability of switching high frequency current will be presented.
-The methodology of analyzing severity of overvoltage in the frequency domain was applied in this project. Results and discussions regarding frequency domain analysis will be shared.
-Simulation results regarding typical system configurations with variation of key parameters such as cable lengths, load power factors will be briefly presented.
-Application of EMTP study results in assisting equipment specification, as well as overvoltage mitigation methods including optimizing switching sequences, necessity of snubber circuits will be discussed.
-Case specific strategies to improve simulation speed and work flow with EMTP will be introduced and discussed.
Author(s): Sofía Aparicio, Andrea Pizzini, Nicolás Morales - UTE
Type:Technical Presentation
Date: 2021-06-21
Abstract
In order to obtain the distances required to perform live working maintenance on the Uruguayan transmission network under secure conditions, electromagnetic transient (EMT) studies are conducted to ob... see moretain the maximum switching overvoltage that can be found in 500-150 kV transmission network. Two different approaches were considered for these studies. On one hand, a simple approach is used, analyzing line switching transients on simplified two line network models. On the other hand, a detailed approach is considered, analyzing line switching overvoltage transients on a complete network model.
This complete model considers 500 kV and 150 kV overhead lines, 500/150 kV transformers, cables, reactive power shunt compensation, hydraulic and thermal generators. Electromagnetic transient studies and the complete network model are performed in EMTP software. Finally, a comparison between the results obtained considering each approach is performed.
Author(s): Angelica Rocha & Gustavo Oliveirra - ATG Engenharia & Federal Univ. of Parana
Type:Technical Presentation
Date: 2021-06-21
Abstract
The presentation will discuss the analysis of successive dielectric failures of inductive voltage transformers (VT) at a 500 kV GIS of Jirau hydroelectric plant in Brazil. All the failures involved th... see moree same region of the high voltage winding and the cause was undetermined. These incidents motivated a series of actions to identify the cause and improve the reliability of these equipment in the field.
One possibility the effect of very fast transients (VFTO) expected to occur during frequent switchings of disconnector and/or circuit-breaker at GIS. It well known that VFTO may stress inductive equipment insulation leading to a dielectric failure.
In this context, different switching conditions were simulated with the EMTP to determine the transient overvoltage at the potential transformer terminals. A special high frequency model of the VT was developed based on its frequency admittance matrix measured in the field. The result of the simulations was discussed together with the VT manufacturer and a final diagnosis of the failures was achieved.
Author(s): N.K.Nathan - KNR Engineers
Type:Technical Presentation
Downloaded: 11
Date: 2021-06-17
Abstract
Gas Insulated Substations provide cost effective solution due to reduced land requirements particularly in metropolitan area where power demand is registering steep growth. With the use of GIS technol... see moreogy, it is required to assess the risk of failure due to overvoltage. The Insulation Coordination study forms a very important aspect in design stage. This presentation deals with the IC study carried out for a large – 765/400/220kV GIS substation in a SUPER THERMAL POWER STATION in UTTAR PRADESH.
Due to the decreasing ratio of lightning impulse withstand voltage to the system voltage, the difference between LIOV and VFTO decreases and this factor calls for VFTO performance analysis for 765kV GIS as well.
The discussion includes modeling of Extra High Voltage GIS, Temporary Overvoltage (TOV), Lightning Impulse Overvoltage (LIOV), Switching Overvoltage (SOV) and Very fast transient Overvoltage (VFTO) performance analysis on 765kV GIS substation.
TOV typically caused by fault to ground, load rejections and energization of long lines are analyzed to decide the rating of the surge arrester.
LIOV simulation studies are carried out for possible onerous paths including longer and short paths to decide the location of the arrester. SOV analysis deals with the overvoltage due to switching operations during line energization, re-energization and fault occurrence and clearance.
The LIOV and SOV results have been validated with reference to protective levels prescribed. The VFTO analysis is performed with various GIS disconnector operations in accordance with the methodology and guidelines as per CIGRE WG D1.03-TB 519 and the results are validated with the limits specified.
Keywords: Insulation Coordination, VFTO, EHV, GIS, 765kV, Protective ratio.