Access to EMTP user presentations, webinars, and slide deck presentations.
158 presentations for EMTP:
Author(s): Henry Gras
Type:Technical Presentation
Date: 2021-08-31
Abstract
This presentation introduce the new Renewable toolbox in EMTP 4.2:
1. New battery device
2. New detailed PV converter with battery and MPPT
3. Initialization improvement
4. M... see moreore modeling flexibility
5. C37.013-2015 implementation
Tag(s): Renewable, PV panels, converter, battery device, wind farm
Author(s): Anton Stepanov
Type:Technical Presentation
Date: 2021-08-31
Abstract
Real-code models/DLLs
- Exact copy of a real control implementation
- Original source code of a controler
Why use real-code DLLs in EMT simulations?
- Ultimate accurac... see morey (same code as onsite)
- Manufacturer's intellectual property is protected
Applications:
- Modeling of windfarms, PV farms, HVDC, exciters, etc.
Tag(s): DLL Interface, control implementation, EMT simulations
Author(s): Neeraj Patel - Adani Power
Type:Technical Presentation
Downloaded: 3
Date: 2021-06-21
Abstract
Unsuccessful auto reclosure has been observed in 765 kV HVAC transmission lines connected with Generation Bus. Back up Impedance Protection of Line reactor triggered during AR dead time due to power f... see morerequency oscillations in faulty phase (disconnected phase). It triggered tripping of Non Switchable Line Reactor at one end, which resulted tripping of 765 kV HVAC Line and avoidable Generation loss.
These Unsuccessful AR operations triggered us to study and model entire phenomena in Power System Analysis software (EMTP).
Initially, two circuits of 765 kV Transmission Line commissioned between Generation Station and Transmission Station with Line Reactor and NGR in both line at either end. Successful auto reclosure observed during single-phase faults on these lines. Intermediate Switching station constructed and both lines were divided in 4 section as per new requirement. Same configuration (rating) of Line Reactor and NGR adopted at newly constructed station on each line. Unsuccessful AR observed during AR running cycle on these lines after new configuration. Backup Impedance protection of Line Reactor found operated during AR Dead time.
Different sets of simulations has been carried out to understand the phenomena:
- Single Phase fault and Auto reclosure in 765 kV Transmission line in different section of entire corridor with Varying Shunt compensation (Value of Line Reactor)
- Different NGR values and observations for above simulations
- Trip the Line Reactor Breaker during Auto Reclosure Phenomena to avoid operation of Backup Impedance protection and its consequences
After EMTP Simulations and study, it was concluded that:
- Line Reactor (Degree of compensation) should be adjusted with adequate value while line length altered from its original design.
- NGR re-sizing can address the issues at some extent. Suitable value of NGR (based on Line Length and amount of shunt compensation) should be employed
Appropriate Solution and mitigation suggested after detail simulation & study.
Tag(s): single pole, analysis, auto reclosure, line reactor
Author(s): Umesh Sen - Power Grid
Type:Technical Presentation
Downloaded: 3
Date: 2021-06-21
Abstract
To meet the increasing power demand, a number of extra high voltage (EHV) transmission lines is being added to the power system network, which enhances the complexity of power system network. It is es... see moresential duty of power engineer to fulfill the growing demand ensuring the reliability, stability & security of GRID. Transient simulation tools like EMTP play a vital role to provide the flexibility to power engineer for simulating/studying the various case scenarios which couldn’t be simulate in physical power system.
Such tools eventually help power engineer to build a sustainable and secure GRID. In POWERGRID, being a central transmission utility, various studies are being carried out to arrive the technical particular of new transmission system and optimize or fine tuning of existing system. Some of them i.e. Transient Recovery Voltage (TRV) study of 1200kV Transmission network, Smart Power from insulated earth wire of EHV transmission line and 1200kV Transformer Inrush current study are discussed in presentation. 1200kV National Test Station was established & successfully charged along with the transmission line in state of BINA in India.
TRV study was carried out for assessment of various test duties of 1200kV Circuit Breaker. Presentation cover the detailed discussion of 1200kV TRV study and a brief about the facilities like HIL, HVDC control Replica setup, STATCOM replica setup available at Powergrid Advanced Research and Technology Centre (PARTeC).
Author(s): Jin Yang - Ener-Phase Solutions
Type:Technical Presentation
Date: 2021-06-21
Abstract
A case study will be presented demonstrating modeling of overvoltage in a moderately sized system involving medium voltage vacuum breakers, cables and transformers. The focus is on simulating high fre... see morequency overvoltage generated by circuit breaker prestrikes and re-ignitions and evaluating the impacts on transformer insulation.
-Results obtained from a customized breaker TRV model which is capable of controlling the capability of switching high frequency current will be presented.
-The methodology of analyzing severity of overvoltage in the frequency domain was applied in this project. Results and discussions regarding frequency domain analysis will be shared.
-Simulation results regarding typical system configurations with variation of key parameters such as cable lengths, load power factors will be briefly presented.
-Application of EMTP study results in assisting equipment specification, as well as overvoltage mitigation methods including optimizing switching sequences, necessity of snubber circuits will be discussed.
-Case specific strategies to improve simulation speed and work flow with EMTP will be introduced and discussed.